The store was looking at replacing their damaged change-room signs. Currently printed on acrylic which was stuck to a polystyrene backing, it was mounted on the wall by a railing system. Due to the location, it has been knocked over a few times. The store has wanted a better finish, scope requested MDF, sprayed with a 2pac finish. Design specifications were provided by the consultant Sign Manager, these details included:
- paint type (Spies Hecker)
- Colour and codes
- substrate
- sizes, thickness, diameter, including a beveled edge to minimise any sharp edges.
- mounting specification
Photos detailed the existing schematics, and the program was to be done within a 5 working day deadline. All works were kept in house to maximise quality control. Our spray booth is now fully functional. Inductions were required working on a Target site, along with Colonial First State new compliance system.
- paint type (Spies Hecker)
- Colour and codes
- substrate
- sizes, thickness, diameter, including a beveled edge to minimise any sharp edges.
- mounting specification
Photos detailed the existing schematics, and the program was to be done within a 5 working day deadline. All works were kept in house to maximise quality control. Our spray booth is now fully functional. Inductions were required working on a Target site, along with Colonial First State new compliance system.
Finished product installed.