We were given a drawing of what to make then we began by getting the materials we needed. The aluminium beams were 6m long and were cut to size and then powder coated. We chose powder-coating because the beams needed to be weatherproof and would be outdoors.
After this, installation began. This install was one story off the ground, so we used a scaffold to install this. We screwed the beams in two places to make sure it was secure, and the total install took 2 full days of work with 2 people working on the first day, and 3 people on the third day.
We do many different types of jobs, so even if its not signage particularly, we are open to installs and home design details. Check our instagram page for images of this.